NEC

TARGETED DATE OF COMPLETION OF THE ON GOING NEC PROJECTS.


Sl.No.Name of ProjectDate of commencementTarget date of completionRemarks
1Integration of New Sub-Stations, Generating Stations under North District with Existing Central Load Dispatch Centre (CLDC) with Facility for Energy Auditing, Sikkim.02.09.201131.07.2015The work is under advanced stage of completion. All works have been completed except commissioning of MUX and VOIP works by the technical commissioning engineers.
2Diversion of 66 KV Tr. Line from Tadong Sub-Station to I.C.A.R Compound in D/C 66 KV tower for independent circuit for Phodong/North Sikkim including improvement of ground clearance of the 66 KV transmission system in North and East Districts.16.12.201131.03.2016Part A: Tadong Sub-station to I.C.A.R compound.
2Diversion of 66 KV Tr. Line from Tadong Sub-Station to I.C.A.R Compound in D/C 66 KV tower for independent circuit for Phodong/North Sikkim including improvement of ground clearance of the 66 KV transmission system in North and East Districts.16.12.201131.03.2016-6 no of 66KV D/C tower completed.
2Diversion of 66 KV Tr. Line from Tadong Sub-Station to I.C.A.R Compound in D/C 66 KV tower for independent circuit for Phodong/North Sikkim including improvement of ground clearance of the 66 KV transmission system in North and East Districts.16.12.201131.03.2016-Dismantling of existing 66KV S/C Tr. Line up to location no. 6 completed.
2Diversion of 66 KV Tr. Line from Tadong Sub-Station to I.C.A.R Compound in D/C 66 KV tower for independent circuit for Phodong/North Sikkim including improvement of ground clearance of the 66 KV transmission system in North and East Districts.16.12.201131.03.2016-One Bay at 66 KV switchyard, Tadong for Dikchu/ Phodong feeder completed.
2Diversion of 66 KV Tr. Line from Tadong Sub-Station to I.C.A.R Compound in D/C 66 KV tower for independent circuit for Phodong/North Sikkim including improvement of ground clearance of the 66 KV transmission system in North and East Districts.16.12.201131.03.2016– Side labeling protective work and equipment foundation for Bay extension at Tadong completed.
2Diversion of 66 KV Tr. Line from Tadong Sub-Station to I.C.A.R Compound in D/C 66 KV tower for independent circuit for Phodong/North Sikkim including improvement of ground clearance of the 66 KV transmission system in North and East Districts.16.12.201131.03.2016– Material for 3 no. of 66 KV S/C towers received.
2Diversion of 66 KV Tr. Line from Tadong Sub-Station to I.C.A.R Compound in D/C 66 KV tower for independent circuit for Phodong/North Sikkim including improvement of ground clearance of the 66 KV transmission system in North and East Districts.16.12.201131.03.2016– Stub-setting of one location at Linkey completed and work in progress.
2Diversion of 66 KV Tr. Line from Tadong Sub-Station to I.C.A.R Compound in D/C 66 KV tower for independent circuit for Phodong/North Sikkim including improvement of ground clearance of the 66 KV transmission system in North and East Districts.16.12.201131.03.2016-Part B: I.C.A.R. to Phudong and North Sikkim.
2Diversion of 66 KV Tr. Line from Tadong Sub-Station to I.C.A.R Compound in D/C 66 KV tower for independent circuit for Phodong/North Sikkim including improvement of ground clearance of the 66 KV transmission system in North and East Districts.16.12.201131.03.2016– 4 no. of 66 KV S/C towers erected.
2Diversion of 66 KV Tr. Line from Tadong Sub-Station to I.C.A.R Compound in D/C 66 KV tower for independent circuit for Phodong/North Sikkim including improvement of ground clearance of the 66 KV transmission system in North and East Districts.16.12.201131.03.2016-8 nos. of stub setting and protective wall completed.
2Diversion of 66 KV Tr. Line from Tadong Sub-Station to I.C.A.R Compound in D/C 66 KV tower for independent circuit for Phodong/North Sikkim including improvement of ground clearance of the 66 KV transmission system in North and East Districts.16.12.201131.03.2016– Work progress hampered due to difficult terrain and frequent blockage of road during rainy season. Limited and scarce land causing delay in accruing land from the owner. Progress, however, is being made for the land acquisition.
3Construction of 10 Nos. Micro Hydels (Total 825 KW) in Sikkim.December 2013 for Sl.No. 3,4,5 & 7.31st March 20161. NOC from the private holders was obtained during inception of the project, however later there was conflict of interest and since land was not available the project stands concelled vide cabinet decision.
3Bala Micro Hydel Project, Assam     Linzey(2×50 KW).September 2014 for31st March 20162. – do –
3Buthang Micro Hydel Project, Assam Linzey, East Sikkim (2×50 KW).Sl.No. 9 & 10.31st March 20163. Power house and intake stricture in advanced stage of completion. There was undue delay in the project implementation for want of forest clearance, which has now been obtained.
3Sawa Micro Hydel Project Dalapchen, East Sikkim (2×50 KW).April 2015 for Sl No.8.31st March 20164. Power house and intake structure in advance stage of completion. The reason for delay is same as stated in Sl.No.3 above.
3Lingtam Micro Hedel Project, Lingtam, East Sikkim (2×50 KW).31st March 20165. Power house, intake structure and Saddle blocks for water conductor in advanced stage of completion, foundation works for forebay completed. The reason for delay is same as stated in Sl.No.3 above.
3Lamaten Micro Hydel Project,(2×50 KW)31st March 20166. Power house frame structure completed. However, forest clearance is awaited for the diversion of forestland for the intake works.
3Kumrek, East Sikkim (2×50 KW).31st March 20167. Power house, intake structure, water conductor and forebay in advanced stage of completion. Some portion of water conductor comprising of HDPE pipes damaged in flash flood i/c one retaining wall. The reason for delay is same as stated in Sl.No.3 above.
3Lower Dalapchen Micro Hydel Project, Dalapchen, East Sikkim (25 KW).31st March 20168. Work was delayed due to delay in obtaining forest clearance and objections from the land owners. The expenditure shown is for material booking from SIMPED. Construction of water conductor is under progress.
3Bakcha Micro Hydel Project (100KW), North Sikkim.31st March 20169. Construction of water conductor and Forebay tank is under progress. The reason for delay is same as Sl.No.3 above.
3B-8 Micro Hydel Project (40KW), North Sikkim.31st March 201610. Construction of water conductor, Forebay Tank and Overflow channel completed. Work of penstock pipe and Power house is under progress. The reason for delay is same as Sl.No.3 above.
3Phensong Micro Hydel Project (60 KW), North Sikkim.31st March 2016
4Construction of 66 KV S/C Tr. Line from 132/66 KV S/Y at Rabongla to Central University with 66/11 KV 2×5 MVA S/Stn. at Yangang, South Sikkim.01.09.201330.08.2015Progress of work slightly low due to land acquisition, rainy season and difficult terrain.
5Procurement, Erection, Testing and Commissioning of 132/66 KV, 20 MVA Power Transformer for 132/66 KV Substation at Kyongsa, Ghalshing, West Sikkim including Electrification of the Chenrezig Shingkham Riwo Potala at Sangha Choeling, Pelling in West Sikkim.09.03.201431.03.2016Part A of the project namely procurement, erection, testing and commissioning of 20 MVA, 132/66 KV S/S at Kyongsa, Gyalshing, West Sikkim have been completed.
5Procurement, Erection, Testing and Commissioning of 132/66 KV, 20 MVA Power Transformer for 132/66 KV Substation at Kyongsa, Ghalshing, West Sikkim including Electrification of the Chenrezig Shingkham Riwo Potala at Sangha Choeling, Pelling in West Sikkim.09.03.201431.03.2016The part B of the project namely Electrification of the Chenrezig Shingkham Riwo Potala at Sangha Choeling, Pelling in West Sikkim is in the tendering process and the work has not as yet been started.