STATUS OF ONGOING AND/OR COMPLETED SCHEMES

 

EXPORT TO EXCEL

SL. No.Name of ProjectLocationDeveloperCapacity (in MW)Nature of AllotmentStatus of DPRDate Of MOU/AgreementScheduled Commercial Operation DateCommissioning month as per MOUTechno-Economic ClearanceEnvironment Impact AssessmentEnvironment Management PlanEnvironment ClearanceLand AcquisitionForest ClearanceLatest StatusOriginal Project Cost (Rs. in crore)Percentage of Equity held by Govt of SikkimFree Share of power to Sikkim (%)Status of Financial ClosureRemarks
1Teesta Stage-IIINorth SikkimTeesta Urja Limited1200BOOTCompleted18-Jul-0560 Months from Financial ClosureDec 13ObtainedCompletedCompletedObtainedCompletedObtainedUnder construction570060.08%12% for 1st 15 years & 15% from 16-35 years---Project achieved COD on 28/02/2017
2Teesta Stage-IVNorth SikkimNHPC Ltd520BOOCompleted01-Mar-06Not specified---ObtainedCompletedCompletedYet to obtain---Stage - I approval accordedMajor construction works still not started---Nil12% for entire life of project---Only preliminary works are under progress. First stage environment clearance is obtained.
3Teesta-VEast SikkimNHPC Ltd510BOONot specifiedProject CommissionedNANil12% for entire life of projectProject commissioned on April 2008
4Teesta Stage-VISouth/East SikkimLanco Energy Pvt Ltd500BOOTCompleted07-Dec-0580 months from MoUJuly 13ObtainedCompletedCompletedObtainedCompletedObtainedWorks on hold300026% (Not infused)12% for 1st 15 years & 15% from 16-35 yearsAchievedProject works suspended due to funding issues. Cummulative progess of the project till date is around 48%. Actions for early revival of the project is under active consideration with all stake holders.
5Panan HEPNorth SikkimHimagiri Hydro Energy Pvt Ltd300BOOTCompleted05-Dec-0572 months from MoUSep 15ObtainedCompletedCompletedObtainedCompletedObtainedPre-construction works started2014.8826% (Not infused)12% for 1st 15 years & 15% from 16-35 yearsUnder ProgressOnly preliminary construction works started due to conditional availibility of Wild life Board Clearance.
6Rongnichu HEPEast SikkimMadhya Bharati Power Corporation96BOOTCompleted01-Mar-0672 Months from MoUDec 18ObtainedIn ProgressIn ProgressObtainedCompletedObtainedUnder construction492.32Nil12% for 1st 15 years & 15% from 16-35 yearsAchievedProject under construction and cummulative progress of the project till date is 64%.
7Chuzachen HEPEast SikkimGati Infrastructures Ltd99BOOTCompleted14-Nov-0336 months from Financial AgreementMay 13ObtainedCompletedCompletedObtainedCompletedObtainedUnder construction448.76Nil12% till 35 years---Project commissioned on 18.06.2013
8Bhasmey HEPEast SikkimGati Infrastructures Ltd51BOOTCompleted14-Nov-032015, DecemberDec 13ObtainedCompletedCompletedObtainedCompletedObtainedUnder construction408.94Nil12% till 35 yearsAchievedUnder construction and cummulative progress of the project till date is arround 28%.
9Rangit-II HEPWest SikkimSikkim Hydro Ventures Ltd66BOOTCompleted08-Dec-0572 months from MoUMar 13ObtainedCompletedCompletedObtainedCompletedObtainedUnder construction496.44Nil12% for 1st 15 years & 15% from 16-35 yearsAchievedUnder construction and cummulative progress of the project till date is around 12%. Promoter has applied for extention of COD.
10Rangit-IV HEPWest SikkimJal Power Corporation Ltd120BOOTCompleted19-Dec-0572 months from MoUJul 15ObtainedCompletedCompletedObtainedCompletedObtainedWorks on hold775.326%12% for 1st 15 years & 15% from 16-35 yearsAchievedProject works suspended due to funding issues. Cummulative progess of the project till date is around 49%. Actions for early revival of the project is under active consideration with all stake holders.
11Dikchu HEPNorth/East SikkimSneha Kinetic Power Projects Ltd96BOOTCompleted01-Mar-0672 months from MoUDec 13ObtainedCompletedCompletedObtainedCompletedObtainedCommissioned499Nil12% for 1st 15 years & 15% from 16-35 yearsAchievedProject decalared COD on 31/3/2017
12Jorethang Loop HEPSouth SikkimDANS Energy Pvt Ltd96BOOTCompleted05-Dec-0572 months from MoUJun 13ObtainedCompletedCompletedObtainedCompletedCompletedCommissioned402.12Nil12% for 1st 15 years & 15% from 16-35 yearsAchievedCOD has been declared w.e.f. 25/09/2015
13Tashiding HEPWest SikkimShiga Energy Pvt. Ltd97BOOTDPR completed03-Sep-0872 months from MoUSep 13ObtainedCompletedCompletedObtainedCompletedObtainedCommissioned494.44Nil12% for 1st 15 years & 15% from 16-35 years & additional 1% for 35 yearsAchievedCOD has been declared w.e.f. 18/10/2017
14Rahi Kyoung HEPNorth SikkimSikkim Engineering Pvt Ltd25BOOTUnder preparation29-Mar-1260 Months from MOUMar 18NoYet to startYet to startNot ObtainedNot StartedYet to applyYet to startNANA12% for 1st 15 years & 15% from 16-35 years & additional 1% for 35 years---Project under survey & investigation. DPR is under preparation. Public hearing has been concluded by SPCB.
15Rangit-III HEPWest SikkimNHPC Limited60BOOProject Commissioned---NA12% for entire life of projectProject commissioned on 15/2/2000
16BakchachuNorth SikkimSanvijay Power and Allied Industries Ltd.40BOOTUnder preparationOnly LOI IssuedNANANAProject under survey & investigation.