Details of IPP Projects Latest (1)


                  ANNEXURE-I
                   
                   
Sl.No Name of Project and Capacity Location Project cost as per TEC in Rs. Cr. Revised cost in Rs. Cr. as on 31st March 2016 Date of award of project Date of completion as per contract Revised proposed date of completion Implementing Agency/ Project Developer Remarks
                   
1 Teesta Stage-II                  330  MW. Revised capacity 150 MW North Sikkim     01.03.2006 Mar-12   Him urja Infra Pvt. Ltd. Project survey & investigation works could not be undertaken due to opposition from Lachen Dzumsa. The project was revised & approved for implementation under Chungthang GP area only whereby the capacity was reduced to 150 MW. The LoI for the revised  capacity had been issued on 17.09.2012. However due to non performence of the developer the project has been withdrawn from Him urja Infra Pvt. Ltd. and termination letter issued on 20.09.2016.
2 Teesta Stage-IV                 520  MW North Sikkim     01.03.2006 Mar-12   NHPC Ltd Only peliminary works are under progress. First stage environment clearance is obtained. Process for public hearing has already been initiated by DC(North). 
3 Teesta Stage-VI                 500 MW South Sikkim 3283 7326 07.12.2005 Dec-11 May-16 Lanco Energy Pvt Ltd Project works suspended due to funding issues. Cummulative progess of the project till date is around 48%. Actions for early revival of the project is under active consideration with all stake holders. 
4 Panan HEP                 300 MW Dzongu, North Sikkim 1833.05 2021.9 05.12.2005 Dec-11 Sep-15 Himagiri Hydro Energy Pvt Ltd Only preliminary construction works started due to conditional availibility of Wild life Board Clearance. NGT case regarding Eco Sensitive Zone is pending at Kolkata.
5 Rongnichu HEP   96 MW Kumrek, East Sikkim 492.32 1187 01.03.2006 Mar-12 Dec-18 Madhya Bharat Power Corporation Project under construction and cummulative progress of the project till date is 64%. 
6 Sada-Mangder HEP   71MW Mangder, West Sikkim     14.11.2003 36 months from date of Financial closure.   Gati Infrastructure Ltd. MoU/IA terminated due to non achievement of the stipulated milestones by the developer on 20.02.2017
7 Bhasmey HEP                 51 MW Bhasmey, East Sikkim   297.76 14.11.2003 14-Feb Mar-18 Gati Infrastructure Ltd. Under construction and cummulative progress of the project till date is  arround 28%.
8 Rangit-II HEP                66 MW West Sikkim 496.44 498 08.12.2005 Dec-12 Dec-15 Sikkim Hydro Ventures Ltd Under construction and cummulative progress of the project till date is around 12%. Promoter has applied for extention of COD.
9 Rangit-IV HEP            120 MW Rothak, West Sikkim 775 1649 19.12.2005 Dec-11 30 months from restart of works. Jal Power Corporation Ltd Project works suspended due to funding issues. Cummulative progess of the project till date is around 49%. Actions for early revival of the project is under active consideration with all stake holders. 
10 Tashiding HEP               97 MW Tashiding, West Sikkim 494.44 984 03.09.2008 Sep-14 Oct-16 Shiga Energy Pvt. Ltd. Project under construction and cummulative progess of the project till date is arround 97 %. The project is expected to be commissioned by June 2017.
11 Kalez Khola-I HEP   27.5 MW West Sikkim     22.03.2011 Mar-17   Cosmic Infra Powergen Pvt. Ltd. MoU/IA terminated due to non performance of the developer on 24.09.2016
12 Kalez Khola-II HEP    54 MW West Sikkim     25.04.2011 Apr-17   Pentacle Power Pvt Ltd MoU/IA terminated due to non performance of the developer on 20.02.2017
13 Rahi Khong HEP 25 MW Dzongu, North Sikkim     29.03.2012 Mar-18   Sikkim Engineering Pvt. Ltd. Project under survey & investigation. DPR is under preparation. Public hearing has been concluded by SPCB.
14 Upper Rolep (Changuchu) HEP 30 MW Rolep, East Sikkim     22.09.2012 Sep-18   Cosmic Infra Powergen Pvt. Ltd. MoU/IA terminated due to non performance of the developer on 24.09.2016
15 Upper Rolep (Nathangchu) HEP 30 MW Rolep, East Sikkim     22.09.2012 Sep-18   Cosmic Infra Powergen Pvt. Ltd. MoU/IA terminated due to non performance of the developer on 24.09.2016
16 Rolep                                36 MW HEP Rolep, East Sikkim     Only LoI issued on 31/12/2010      Velankani Renewable Energy Pvt. Ltd. A arbitration case is underway with the M/s Amalgated Transelectric (India) Power Ltd. (ATPIL). The projects was allotted to this company in 2002. The arbitration proceedings have been completed on 7/5/2017and final award is awaited.
17  Ralang 40 MW & MW HEP Ralang, South Sikkim     Only LoI issued on 31/12/2010      Velankani Renewable Energy Pvt. Ltd.
18  Chakungchu 50 MW HEP Chakhangchu, North Sikkim     Only LoI issued on 31/12/2010      Velankani Renewable Energy Pvt. Ltd.
19 Suntaleytar HEP 40 MW Suntaleytar, East Sikkim     Only LoI issued on 23/02/2012      Moser Baer Electric Power Limited DPR prepared and completed by CWC and submitted to the Energy & Power Deptt. Due to non performance of the developer the LoI has been terminated on 20/2/2017.   
20 Rechu-Meyongchu HEP                              26 MW Rechu, North Sikkim     Only LoI issued on  Sept 2012     Planet Infra Pojects Pvt ltd. MoU/IA terminated due to non performance of the developer on 20.09.2016
21 Bakchachu 30 MW  Bakcha, North Sikkim     Only LoI issued on 02.06.2012      Samvijay Power & Allied Industries ltd. Project under survey & investigation.
22 Manul & Mangan 30 MW Manul, North Sikkim     Only LoI issued on 22.09.2012      Higen Power Pvt. Ltd.Higen MoU/IA terminated due to non performance of the developer on 20.09.2017
23 Lachung HEP, 99 MW, North Sikkim Lachung, North Sikkim     18.01.2008 As per revised time lines Nov 2015 Nov-21   Lachung Power Pvt. Ltd. Project was terminated as milestones could not be achieved. DPR could not be prepared as survey & investigation of the Project could not be carried out even after 4 years of signing of the MOU/IA due to local resistance. MOU/IA was terminated by the Govt. on June 2012. Termination order of the project was challanged by the developer in the High Court of Sikkim. As per the directives of the High Court new time lines up to 2018 has been given to the promoter for the devlopment of these projects. DC(North) is coordinating to hold meetings with the local stake holders.
24 Bimkyong HEP, 99 MW, North Sikkim Bimkyong, North Sikkim     18.01.2008 As per revised time lines Nov 2015 Nov-21   Teesta Power Pvt. Ltd.
25 Bop HEP, 99 MW, North Sikkim Chungthang, North Sikkim     18.01.2008 As per revised time lines Nov 2015 Nov-21   Chungthang Hydro Power Pvt. Ltd.
26 Teesta Stage-III       1200 MW North Sikkim 5700 13965 18.07.2005 Sep-12 Mar-17 Teesta Urja Ltd. Project under construction and cummulative progress of the project till date is 98.8%. First three units of 200 MW each are ready for generation once priority transmission line is completed. All units are expected to be commissioned by DEC 2016.
27 Dikchu HEP                   96 MW Dikchu, North Sikkim 499 1140 01.03.2006 Mar-12 Mar-17 Sneha Kinitic Power  Project Ltd Project under advance stage of construction. Cummulative progess of the project till date is around 94%. Expected date of commissioning is end of December 2016.
28 Rangit-III HEP              60 MW Hingdam, South Sikkim           NHPC Limited Project commissioned
29 Teesta-V HEP                     510 MW Balutar, East Sikkim           NHPC Limited Project commissioned
30 Chuzachen HEP 99 MW Chujachen, East Sikkim 448.76 1188.57 14.11.2003 Mar-10   Gati Infrastructure Ltd. Project commissioned on 18.06.2013
31 Jorethang Loop HEP 96 MW Majitar, South Sikkim 402.12 1518.52 5.12.2005 Mar-12   DANS Energy Pvt Ltd Project is commissioned. COD has been declared w.e.f. 25/09/2015 

 

Projects which are commissioned:     Developer        
    1 Rangit-III HEP 60 MW NHPC        
    2 Teesta-V HEP 510 MW NHPC        
    3 Chujenchen HEP 110 MW Gati Infrastructure Ltd.      
    4 Jorethang Loop HEP             96 MW Dans Energy Pvt. Ltd.      
    5 Teesta-III HEP 1200 MW Teesta Urja Ltd.      
    6 Dikchu HEP 96 MW Sneha Kinetic Power Projects Pvt. Ltd. Commissioned on 31st April 2017 
      Total: 2072 MW          

 