ANNEXURE-I | |||||||||
Sl.No | Name of Project and Capacity | Location | Project cost as per TEC in Rs. Cr. | Revised cost in Rs. Cr. as on 31st March 2016 | Date of award of project | Date of completion as per contract | Revised proposed date of completion | Implementing Agency/ Project Developer | Remarks |
1 | Teesta Stage-II 330 MW. Revised capacity 150 MW | North Sikkim | 01.03.2006 | Mar-12 | Him urja Infra Pvt. Ltd. | Project survey & investigation works could not be undertaken due to opposition from Lachen Dzumsa. The project was revised & approved for implementation under Chungthang GP area only whereby the capacity was reduced to 150 MW. The LoI for the revised capacity had been issued on 17.09.2012. However due to non performence of the developer the project has been withdrawn from Him urja Infra Pvt. Ltd. and termination letter issued on 20.09.2016. | |||
2 | Teesta Stage-IV 520 MW | North Sikkim | 01.03.2006 | Mar-12 | NHPC Ltd | Only peliminary works are under progress. First stage environment clearance is obtained. Process for public hearing has already been initiated by DC(North). | |||
3 | Teesta Stage-VI 500 MW | South Sikkim | 3283 | 7326 | 07.12.2005 | Dec-11 | May-16 | Lanco Energy Pvt Ltd | Project works suspended due to funding issues. Cummulative progess of the project till date is around 48%. Actions for early revival of the project is under active consideration with all stake holders. |
4 | Panan HEP 300 MW | Dzongu, North Sikkim | 1833.05 | 2021.9 | 05.12.2005 | Dec-11 | Sep-15 | Himagiri Hydro Energy Pvt Ltd | Only preliminary construction works started due to conditional availibility of Wild life Board Clearance. NGT case regarding Eco Sensitive Zone is pending at Kolkata. |
5 | Rongnichu HEP 96 MW | Kumrek, East Sikkim | 492.32 | 1187 | 01.03.2006 | Mar-12 | Dec-18 | Madhya Bharat Power Corporation | Project under construction and cummulative progress of the project till date is 64%. |
6 | Sada-Mangder HEP 71MW | Mangder, West Sikkim | 14.11.2003 | 36 months from date of Financial closure. | Gati Infrastructure Ltd. | MoU/IA terminated due to non achievement of the stipulated milestones by the developer on 20.02.2017 | |||
7 | Bhasmey HEP 51 MW | Bhasmey, East Sikkim | 297.76 | 14.11.2003 | 14-Feb | Mar-18 | Gati Infrastructure Ltd. | Under construction and cummulative progress of the project till date is arround 28%. | |
8 | Rangit-II HEP 66 MW | West Sikkim | 496.44 | 498 | 08.12.2005 | Dec-12 | Dec-15 | Sikkim Hydro Ventures Ltd | Under construction and cummulative progress of the project till date is around 12%. Promoter has applied for extention of COD. |
9 | Rangit-IV HEP 120 MW | Rothak, West Sikkim | 775 | 1649 | 19.12.2005 | Dec-11 | 30 months from restart of works. | Jal Power Corporation Ltd | Project works suspended due to funding issues. Cummulative progess of the project till date is around 49%. Actions for early revival of the project is under active consideration with all stake holders. |
10 | Tashiding HEP 97 MW | Tashiding, West Sikkim | 494.44 | 984 | 03.09.2008 | Sep-14 | Oct-16 | Shiga Energy Pvt. Ltd. | Project under construction and cummulative progess of the project till date is arround 97 %. The project is expected to be commissioned by June 2017. |
11 | Kalez Khola-I HEP 27.5 MW | West Sikkim | 22.03.2011 | Mar-17 | Cosmic Infra Powergen Pvt. Ltd. | MoU/IA terminated due to non performance of the developer on 24.09.2016 | |||
12 | Kalez Khola-II HEP 54 MW | West Sikkim | 25.04.2011 | Apr-17 | Pentacle Power Pvt Ltd | MoU/IA terminated due to non performance of the developer on 20.02.2017 | |||
13 | Rahi Khong HEP 25 MW | Dzongu, North Sikkim | 29.03.2012 | Mar-18 | Sikkim Engineering Pvt. Ltd. | Project under survey & investigation. DPR is under preparation. Public hearing has been concluded by SPCB. | |||
14 | Upper Rolep (Changuchu) HEP 30 MW | Rolep, East Sikkim | 22.09.2012 | Sep-18 | Cosmic Infra Powergen Pvt. Ltd. | MoU/IA terminated due to non performance of the developer on 24.09.2016 | |||
15 | Upper Rolep (Nathangchu) HEP 30 MW | Rolep, East Sikkim | 22.09.2012 | Sep-18 | Cosmic Infra Powergen Pvt. Ltd. | MoU/IA terminated due to non performance of the developer on 24.09.2016 | |||
16 | Rolep 36 MW HEP | Rolep, East Sikkim | Only LoI issued on 31/12/2010 | Velankani Renewable Energy Pvt. Ltd. | A arbitration case is underway with the M/s Amalgated Transelectric (India) Power Ltd. (ATPIL). The projects was allotted to this company in 2002. The arbitration proceedings have been completed on 7/5/2017and final award is awaited. | ||||
17 | Ralang 40 MW & MW HEP | Ralang, South Sikkim | Only LoI issued on 31/12/2010 | Velankani Renewable Energy Pvt. Ltd. | |||||
18 | Chakungchu 50 MW HEP | Chakhangchu, North Sikkim | Only LoI issued on 31/12/2010 | Velankani Renewable Energy Pvt. Ltd. | |||||
19 | Suntaleytar HEP 40 MW | Suntaleytar, East Sikkim | Only LoI issued on 23/02/2012 | Moser Baer Electric Power Limited | DPR prepared and completed by CWC and submitted to the Energy & Power Deptt. Due to non performance of the developer the LoI has been terminated on 20/2/2017. | ||||
20 | Rechu-Meyongchu HEP 26 MW | Rechu, North Sikkim | Only LoI issued on Sept 2012 | Planet Infra Pojects Pvt ltd. | MoU/IA terminated due to non performance of the developer on 20.09.2016 | ||||
21 | Bakchachu 30 MW | Bakcha, North Sikkim | Only LoI issued on 02.06.2012 | Samvijay Power & Allied Industries ltd. | Project under survey & investigation. | ||||
22 | Manul & Mangan 30 MW | Manul, North Sikkim | Only LoI issued on 22.09.2012 | Higen Power Pvt. Ltd.Higen | MoU/IA terminated due to non performance of the developer on 20.09.2017 | ||||
23 | Lachung HEP, 99 MW, North Sikkim | Lachung, North Sikkim | 18.01.2008 As per revised time lines Nov 2015 | Nov-21 | Lachung Power Pvt. Ltd. | Project was terminated as milestones could not be achieved. DPR could not be prepared as survey & investigation of the Project could not be carried out even after 4 years of signing of the MOU/IA due to local resistance. MOU/IA was terminated by the Govt. on June 2012. Termination order of the project was challanged by the developer in the High Court of Sikkim. As per the directives of the High Court new time lines up to 2018 has been given to the promoter for the devlopment of these projects. DC(North) is coordinating to hold meetings with the local stake holders. | |||
24 | Bimkyong HEP, 99 MW, North Sikkim | Bimkyong, North Sikkim | 18.01.2008 As per revised time lines Nov 2015 | Nov-21 | Teesta Power Pvt. Ltd. | ||||
25 | Bop HEP, 99 MW, North Sikkim | Chungthang, North Sikkim | 18.01.2008 As per revised time lines Nov 2015 | Nov-21 | Chungthang Hydro Power Pvt. Ltd. | ||||
26 | Teesta Stage-III 1200 MW | North Sikkim | 5700 | 13965 | 18.07.2005 | Sep-12 | Mar-17 | Teesta Urja Ltd. | Project under construction and cummulative progress of the project till date is 98.8%. First three units of 200 MW each are ready for generation once priority transmission line is completed. All units are expected to be commissioned by DEC 2016. |
27 | Dikchu HEP 96 MW | Dikchu, North Sikkim | 499 | 1140 | 01.03.2006 | Mar-12 | Mar-17 | Sneha Kinitic Power Project Ltd | Project under advance stage of construction. Cummulative progess of the project till date is around 94%. Expected date of commissioning is end of December 2016. |
28 | Rangit-III HEP 60 MW | Hingdam, South Sikkim | NHPC Limited | Project commissioned | |||||
29 | Teesta-V HEP 510 MW | Balutar, East Sikkim | NHPC Limited | Project commissioned | |||||
30 | Chuzachen HEP 99 MW | Chujachen, East Sikkim | 448.76 | 1188.57 | 14.11.2003 | Mar-10 | Gati Infrastructure Ltd. | Project commissioned on 18.06.2013 | |
31 | Jorethang Loop HEP 96 MW | Majitar, South Sikkim | 402.12 | 1518.52 | 5.12.2005 | Mar-12 | DANS Energy Pvt Ltd | Project is commissioned. COD has been declared w.e.f. 25/09/2015 |
Projects which are commissioned: | Developer | ||||||||
1 | Rangit-III HEP | 60 MW | NHPC | ||||||
2 | Teesta-V HEP | 510 MW | NHPC | ||||||
3 | Chujenchen HEP | 110 MW | Gati Infrastructure Ltd. | ||||||
4 | Jorethang Loop HEP 96 MW | Dans Energy Pvt. Ltd. | |||||||
5 | Teesta-III HEP | 1200 MW | Teesta Urja Ltd. | ||||||
6 | Dikchu HEP | 96 MW | Sneha Kinetic Power Projects Pvt. Ltd. | Commissioned on 31st April 2017 | |||||
Total: | 2072 MW |